1.
The normal time required for the completion of project in the above problem is
2.
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
3.
A construction schedule is prepared after collecting
4.
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
5.
Bar charts are suitable for
6.
The first stage of a construction, is
7.
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be
8.
The probability of completion of any activity within its expected time is
9.
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
10.
Time and progress chart of a construction, is also known as