A project manager has been assigned two team members who do not get along. On past projects they have
proven very difficult to work with and are often at odds with one another. Which of the following conflict
resolution techniques would be BEST to address this?
A project manager added some experienced team members to work on certain project activities in conjunction
with inexperienced team members because the project is behind schedule. Which of the following BEST
describes the technique the project manager is using?
A team member reports that a system component they are working on causes the system to continually reboot.
The project manager should record this in which of the following documents?
A project manager is working with a large team on an important project. Many of the team members work
remotely. The project manager requires each team member to submit weekly status reports at a certain time
each week. One team member consistently submits late status reports. Which of the following should the
project manager consider FIRST?
An experienced team member comes to the project manager to report that they are uncertain of the project
requirements. This can MOST likely be attributed to: