A project team member informs the project manager that they have added functionality to enhance the product.
The team member did not inform the project manager prior to making the change. Which of the following
should the project manager do in this situation?
During execution of the project, the project sponsor informs the project manager that a requirement needs to be
added to the scope statement. Which of the following is the FIRST action that the project manager should
take?
Various technologies exist to complete a project, but the project manager is not well versed in these technologies. Which of the following can the project manager initiate to assist with the decision?
Several project team members are in conflict about the lighting in their office and the noise level. Which of the
following describes this type of conflict?