An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other
vendors in an attempt to get the other vendors to underbid the original price quoted is referred to
as:
NO: 37
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of
your split screen, using the drop down menu, to reference during your response/choice of responses.
The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been
welded or flushed. What percent complete is this project?
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of
your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is
determined to be 66% complete. Based on current trends, how many hours will be expended at project
completion?
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of
your split screen, using the drop down menu, to reference during your response/choice of responses.
10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many
hours were planned?
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of
your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1
decimal)
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of
your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, the final price for the piece of equipment will be:
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of
your split screen., using the drop down menu, to reference during your response/choice of responses.
What is the range of unit costs?