What type of planning is used where the work to be accomplished in the near term is planned in detail,
while work in the future is planned at a higher level?
What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size,
weight, and complexity from a previous, similar project as the basis for estimating the same parameter or
measure for a future project?