1.
Which process includes facilitated workshops as a tool and technique?
2.
Which of the following is a tool or technique used to verify scope?
3.
Inspection is a tool and technique for which of the following processes?
4.
What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably estimated and managed?
5.
Many organizations categorize requirements into which of the following two categories?
6.
Plurality is a type of which of the following?
7.
Which of the following events would result in a baseline update?
8.
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
9.
Which schedule development technique modifies the project schedule to account for limited resources?
10.
Which schedule development tool and technique produces a theoretical early start date and late start date?