Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of
Week 16 of the project, the following information is collected:
Actual cost = $50,000
Plan cost = $45,000
Earned value = $40,000
What is the cost performance index?