1.
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
2.
Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?
3.
Which technique is utilized in the Schedule Control process?
4.
Cost baseline is an output of which of the following processes?
5.
Analogous Cost Estimating relies on which of the following techniques?
6.
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of
Week 16 of the project, the following information is collected:
Actual cost = $50,000
Plan cost = $45,000
Earned value = $40,000
What is the cost performance index?
7.
The PV is $1000, EV is $2000 and AC is $1500. What is CPI?
8.
At the end of the project, what will be the value of SV?
9.
Which is one of the determining factors used to calculate CPI?
10.
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?