A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.
What is the cost variance?
As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?