1.
Instead of celebrating the end of the project, the stakeholders are breathing a sigh of relief. None of them were confident the project would meet the end date. Which of the following is NOT one of the reasons this project had difficulty?
2.
A project manager for a small construction company has a project that was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it
has cost US $90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the PRIMARY responsibility to solve this problem?
3.
While reviewing project performance, the project manager determines that the schedule variance is -500.
What is the BEST thing to do?
4.
The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know how long the project will take if only nine resources each month are committed to your project.
What is this activity called?
5.
A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews. The project is 40 percent complete and has used 60 percent of the available calendar time.
What is the FIRST thing you should do?
6.
To accommodate a new project in your department, you need to move resources from one project to another. Because your department is currently working at capacity, moving resources will inevitably delay
the project from which you move the resources. It would cause the LEAST negative impact if you move resources from which of the following projects?
7.
Who has the cost risk in a fixed price (FP) contract?
8.
The project management office is worried about the quality of the company's various projects. They want to know which projects are having problems and which ones are doing well. If the PMO receives the following information, which project should they be the MOST concerned about?
9.
Earned value measurement is an example of:
10.
A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of
spilled rock per day. In which of the following does the project manager document quality control, quality assurance, and quality improvements for this project?